Hangingstone Expansion Project

Client

Japan Canada Oil Sands Ltd.

Schedule

2013 - 2016

Industry

Energy

Our scope of work for this project was the role of EPC Contractor. Our scope was to provide all necessary engineering, procurement, construction management, dire hire construction, pre-commissioning services, and required site infrastructure. Bemac was responsible for all necessary construction management, dire hire construction, pre-commissioning services, and required site infrastructure. Bantrel provided EPC services for the project scope, which included:

  • Field Facilities: (6) SAGD well pads, each with (32) well pairs, (6) process buildings, (6) MCC, instrument utility buildings, (6) pop tanks with containment areas, and (6) steam letdown modules.
  • Above Ground Pipeline: 900 # steam (approximately 5 km), 300 # produced gas (approximately 5 km), 300 # produced emulsion (approximately 5 km), 5 drain stations, and 4 valve stations.
  • Below Ground Pipeline: 600 # natural gas (approximately 5 km) and 300 # quench water (approximately 5 km). The below ground pipelines construction scope included:
    • Obtaining necessary permitting and crossing agreements
    • Excavation and backfilling of bore pits
    • Horizontal directional drilling
    • Hydrovacing
    • Installation of Fiberspar piping
    • Hydrotesting; and
    • Restoring Muskeg ROWs

Bemac also has a relationship with Whitefish Lake First Nation in the Bonnyville, St. Paul area. Skilled Trades were recruited from the Nation to work on JACOS Hangingstone Expansion Project.

Services Provided

  • Engineering
  • Procurement
  • Construction

Completed By

  • Bemac Construction Corp.